1. Home
  2. Guides
  3. How Deep Should Foundations Be?
UK trade guide

How Deep Should Foundations Be?

How deep and wide to dig a strip foundation for a garden wall or an extension, why clay and trees change everything, and a trench planner priced at UK merchant prices, last checked on the date shown.

Page last reviewed 25 October 2026 by the UkToolCalc team

The foundation is the cheapest part of a wall or extension to get right and the most expensive to put right. Most cracks you see in garden walls and extensions trace back to one thing: a footing that wasn't deep enough for the ground it sits in. This guide gives typical UK depths for each job and soil, explains why clay and trees matter so much, and walks through digging and pouring. The trench planner prices the concrete for your trench.

A mini excavator digging a foundation trench in a garden
A mini digger and a day of good weather: the start of every solid wall and extension.
  • 450mmminimum depth on firm sand or gravel (frost)
  • 0.75–1mon clay, by how much it shrinks
  • 2.5m+possible on clay near trees
  • 150mmminimum concrete; 225mm is common

1. Why depth matters: frost, clay and trees

A footing has to sit on ground that won't move. Three things move ground in the UK:

  • FrostWater in the top 450mm or so freezes, swells and lifts anything resting on it.
  • Shrinkable claySwells when wet and shrinks in dry summers, sometimes metres down.
  • TreesOn clay, roots drink the ground dry and make it shrink far deeper.

2. Typical depths by soil

These are starting points for walls and single-storey extensions, from Building Regulations guidance (Approved Document A) and NHBC Standards. For an extension, building control confirms the depth on site.

Minimum foundation depths drawn to scale: 450mm on firm sand or gravel, 750mm on low-shrinkage clay, 900mm on medium, 1m on high-shrinkage clay, and up to 2.5m or more on clay near trees Sand orgravel Clay:low Clay:medium Clay:high Clay neartrees 450mm 750mm 900mm 1m up to 2.5m+
Minimum depths to the bottom of the footing, to scale. Grey is the concrete; every one sits on firm, undisturbed ground.
JobTypical trench depthFooting widthConcrete
Garden wall up to 1m, single skin450–600mm, to firm ground~450mm150–225mm
Garden wall 1–2m, double skin600mm+, to firm ground~600mm225mm
Extension on firm sand or gravel450mm minimum (often 1m in practice)~600mm225mm
Extension on shrinkable clay0.75–1m minimum~600mm225mm, or trench fill
Clay near treesFrom NHBC tables: often 1.5–2.5m~600mmTrench fill; engineer over 2.5m

3. Know your ground before you dig

  • Sand or gravelGritty, drains fast. Good ground: 450mm for frost.
  • ClaySticky, rolls into a sausage, cracks when dry. Dig 0.75–1m or more.
  • Made groundOld rubble or fill: dig through it to natural ground, or get advice.
  • Roots or soft spotsCut roots over 50mm need advice; dig soft pockets out and fill with concrete.

Not sure what you have? Dig a trial hole to the planned depth first, and ask building control or your local authority. On an extension they'll often tell you the depth they'd expect on your street.

4. Width, thickness and trench fill

Cross-section of a strip foundation for a cavity wall: a 600mm-wide trench dug to firm ground, 225mm of concrete at the bottom projecting beyond the wall on each side by no more than the concrete's thickness, blockwork up to ground level, and the damp-proof course at least 150mm above the ground 600mm wide DPC 150mm+above ground Ground 225mmconcrete Dig tofirm, naturalground Projection≤ thickness
A strip foundation for a cavity wall, roughly to scale. The concrete sticks out each side by no more than its own thickness.
  • Width: wide enough to spread the wall's weight. About 600mm is typical for an extension wall; 450mm suits a single-skin garden wall.
  • Thickness: at least 150mm, and at least as thick as the footing sticks out past the wall face. 225mm is the usual choice.
  • Trench fill: on clay or deep trenches, many builders fill the trench with concrete to within about 150mm of the ground instead. It uses more concrete but saves laying blocks in a deep, narrow trench, and is often quicker and safer.
  • Steps: on a slope, step the footing rather than slope it. Each step overlaps the one below by at least the concrete thickness.

5. Plan and price your trench

Enter your trench and the planner works out the concrete, the bags to mix it on site (or the ready-mix to order) and the spoil to get rid of, priced at the cheapest UK merchant we've found. It uses the same maths as the foundation calculator.

m
Along the centre of the trench.
mm

The planner needs JavaScript. You can still use the foundation calculator.

Assumes 10% extra concrete for uneven trench sides, a 1:6 cement and all-in ballast mix (about 2,050kg of dry mix per m³), 850kg bulk bags, ready-mix in 0.25m³ steps with a 1m³ minimum, and spoil bulking up by 30% (about 1.8 tonnes per m³ dug). Ready-mix prices vary too much by area to track.

6. Digging and pouring, step by step

  1. Tell building control before you start, for an extension. Book the trench inspection for the day you finish digging.
  2. Set out the trench with pegs and string lines, and mark it with spray paint. Check for drains, pipes and cables first.
  3. Dig to depth with straight sides and a flat, clean bottom on firm ground. Don't leave it open in rain longer than you must: wet clay softens.
  4. Get it inspected. The inspector may ask you to go deeper if the ground isn't right. Pour as soon as possible after they approve it.
  5. Set level pegs in the trench with their tops at the finished concrete level, checked with a laser or long level.
  6. Pour in one go if you can. Over about 1m³, ready-mix straight from the lorry (or a pump) is far easier than mixing on site.
  7. Compact and level the concrete to the pegs, working out the air with a shovel or a hired poker.
  8. Cover and wait. Keep it damp and protected from frost, and give it a few days before building on it.

7. Mistakes that crack walls

  • Too shallowFrost or shrinking clay moves it, and the wall cracks.
  • On topsoil or fillAlways dig through to firm, natural ground.
  • Ignoring treesOn clay, a tree nearby can mean metres deeper.
  • Pouring into waterPump the trench out; standing water weakens the concrete.
  • Pouring in batches days apartCold joints are weak spots. Pour in one go.
  • Skipping the inspectionBuilding control may ask you to dig it up.

8. Foundation checklist

Print this page (the planner is left out of the printout) and tick these off as you go:

  • Building control notified (extensions), trench inspection booked
  • Soil checked with a trial hole; trees within about 20m noted
  • Depth, width and concrete thickness agreed
  • Drains, pipes and cables found; skip or grab lorry booked for the spoil
  • Trench dug to firm, natural ground with a flat, clean bottom
  • Trench inspected and approved
  • Level pegs set to the finished concrete level
  • Concrete poured in one go, compacted and levelled
  • Concrete covered and kept from frost while it hardens

Building a wall on it? See the garden wall guide, or work out the spoil with the excavation calculator and a skip with the skip size calculator.

Frequently asked questions

How deep should foundations be in the UK?

At least 450mm below ground on firm sand or gravel, to get below the frost. On clay soils, which shrink and swell, NHBC guidance gives at least 750mm on low-shrinkage clay, 900mm on medium and 1m on high-shrinkage clay, and deeper near trees, sometimes 2.5m or more. In every case the bottom must be on firm, undisturbed ground, and building control has the final say for an extension.

How wide should a strip foundation be?

For a typical single-storey extension, 600mm wide is common. A garden wall usually needs about 450mm for single skin and 600mm for double skin. The footing should project beyond the wall on each side, and the concrete should be at least as thick as that projection.

How thick should the concrete be in a footing?

At least 150mm, and never less than the amount the footing sticks out beyond the wall. 225mm is a common thickness for extensions. On clay, many builders use trench fill instead: concrete poured to within about 150mm of the ground.

Do I need building control for foundations?

For an extension, yes. You (or your builder) notify building control before work starts, and an inspector checks the open trench before any concrete goes in. A garden wall doesn't need approval, but the same depth rules keep it standing.

How close can I build to a tree?

On clay, trees draw water out of the ground and make it shrink, so foundations near them must go much deeper. How deep depends on the tree species, its mature height and the distance. NHBC Chapter 4.2 has the tables; building control or an engineer will tell you the depth for your site.

Seasonal building tips, once a month

What to get done before the frosts, the storms and the spring rush, plus new calculators and guides. Free, no spam, unsubscribe in one click.

Get the tips

Related calculators

Tools & materials for this job

Affiliate links: as an Amazon Associate we earn from qualifying purchases, at no extra cost to you.