Quick answer

How Many m² Does a Tonne of MOT Type 1 Cover?

MOT Type 1 sub-base at about 2.1 tonnes per m³ once compacted, no allowance for waste.

Page last reviewed 26 October 2026 by the UkToolCalc team

One tonne of MOT Type 1 covers about 4.8m² at 100mm compacted depth. An 850kg bulk bag covers about 4m².

Work out your own in the MOT Type 1 Sub-Base calculator
  • 4.8m²per tonne at 100mm
  • ~4m²per 850kg bag at 100mm
  • 2.1 tper m³ compacted
  • 0.21 tper m² at 100mm

MOT Type 1: tonnes to m²

Compacted depth, no allowance for waste (add 5–10%).

Compacted depthm² per tonnem² per 850kg bagTonnes per m²Typical use
50 mm9.58.10.11Topping up an old base
75 mm6.35.40.16Paths on firm ground
100 mm4.84.00.21Patios, shed bases
150 mm3.22.70.32Driveways, clay ground

The sum

m² per tonne = 1 ÷ (2.1 × depth in metres) 100mm: 1 ÷ (2.1 × 0.1) = 4.8m²

The MOT Type 1 calculator turns your area into tonnes and bulk bags, with membrane and compaction layers.

Frequently asked questions

Why does MOT cover less than gravel?

It's compacted. Loose MOT Type 1 is about 1.6–1.7 tonnes per m³, but once rolled or wacked it packs down to about 2.1 tonnes per m³, so each tonne fills less depth.

How many tonnes of MOT per m²?

About 0.21 tonnes per m² at 100mm compacted, 0.16 at 75mm and 0.32 at 150mm.

What depth of MOT do I need?

75mm for paths on firm ground, 100mm for patios and shed bases, and 150mm for driveways and soft or clay ground.