Quick answer

What Size Skip Do I Need for Muck Away?

Clay or subsoil, which swells by about 30% once dug and weighs about 1.9 tonnes per m³ in the ground.

Page last reviewed 26 October 2026 by the UkToolCalc team

Digging out a 4 × 3m patio 250mm deep gives about 3.9m³ of loose soil that weighs about 5.7 tonnes. It fits in one 6-yard skip by volume, but weight is the real limit: ask the hire firm before you fill it.

Work out your own in the Excavation & Muck-Away calculator
  • +30%clay swells once dug
  • 1.9 tper m³ of clay in the ground
  • Weightfills a skip before volume
  • 12m³per grab lorry load

Muck away by job

Clay or subsoil, 6-yard skips (about 4.6m³), counted by volume only. Bags are 1 tonne builders' bags.

JobDug (in ground)Loose volumeWeight6-yard skipsOr tonne bags
Shed base 3 × 2m, 150mm0.9 m³1.2 m³1.7 t12
Patio 3 × 3m, 200mm1.8 m³2.3 m³3.4 t14
Wall footing 10m × 450 × 600mm2.7 m³3.5 m³5.1 t16
Patio 4 × 3m, 250mm3.0 m³3.9 m³5.7 t16
Drive 6 × 4m, 250mm6.0 m³7.8 m³11.4 t2 (or 1 grab)12

The skip counts are by volume. With soil this heavy, ask the hire firm for its weight limit: if it's lower than the weight in the table, you'll need more skips or a grab lorry.

The sum

Loose volume = length × width × depth × 1.3 (clay) Weight = length × width × depth × 1.9 t

The excavation calculator covers other soils, trenches and post holes, and checks the skips against your hire firm's weight limit.

Frequently asked questions

Why does dug soil take up more room?

Soil 'bulks' once it's dug: the packed ground breaks into loose lumps with air between them. Clay grows by about 30%, topsoil by about 25% and broken concrete by up to 60%.

Can I fill a skip to the top with soil?

Usually not. Soil and rubble are so heavy that most skips hit their weight limit long before they're full. Many hire firms only allow heavy waste in smaller skips, or ask you to fill them part-way.

Is a grab lorry better than a skip for muck away?

For more than about 8–10m³ of loose soil, often yes. A grab lorry takes around 12m³ (up to about 16 tonnes) in one go, needs no permit and can reach over a wall or hedge.